What are the precautions for the removal of disc scaffolding?

The risk of dismantling disc-buckle scaffolding is far greater than that of erection work, because when dismantling disc-buckle scaffolding, concrete pouring has already been completed, which makes dismantling disc-buckle scaffolding more troublesome than erection. So, what are the precautions for dismantling disc scaffolding? Let’s take you to find out.

Disc buckle scaffolding is to create construction operating conditions for high-altitude operations. The demolition plan should be drawn up according to the specific conditions of the demolition of the shelf. The scaffolding personnel should dismantle the shelf according to the plan, and pay attention to the following issues:

01. Set up disc-buckle scaffolding to remove the restricted area, and set up special personnel to supervise it. During the operation, the on-site personnel are prohibited from entering the restricted area.

02. The personnel who remove the disc-buckle scaffold must wear safety belts, helmets, and rubber-soled shoes.

03. Dismantling the disc-buckle scaffolding is not allowed to work up and down at the same time, it must be removed layer by layer. The dismantled pieces must be loosened one by one, taken out one by one, and then hung down immediately. The dismantled materials should also be removed and cleaned up. It is strictly forbidden to throw the dismantled rods downwards from a high place.

04. Dismantling disc-buckle scaffolding is usually a group of 2 to 3 people, working collaboratively, taking pictures and supervising each other. When feeding materials from the shelf down, they must cooperate up and down to respond from the top to the bottom. Avoid single-person dismantling operations, because single-person operations are prone to accidents due to unstable and unbalanced holding rods.

05. When dismantling the disc-buckle scaffolding, it should be removed in the order of up and down, outside and inside, surface material first, structural material first, auxiliary parts first, structural parts first, structural parts first, and wall parts first. The principle of arbitrary removal.