Scaffolding matting specification requirements

The specification of scaffolding mat board requires the use of wooden mat board, the specification requirements for the long side should be more than 2 spans, with a thickness of more than 50 millimeters, the width should be more than 200 millimeters.

Double-row scaffolding should be set up with scissor braces and transverse diagonal impact, single-row scaffolding should be set up with scissor braces. The width of each scissor struck should not be less than 4 spans, the eye should not be less than 6m, and the inclination angle between the diagonal bar and the ground should be between 45°~60°.

The height of 24m below the single, double row scaffolding, must be set up in the outer facade of each end of a scissors crash, and should be set up from the bottom to the top of the continuous; the middle of the scissors between the distance between the channel should not be greater than 15m. height of more than 24m double row scaffolding should be set up in the outer facade throughout the length and height of the shear braces continuously.

Ground/Surface Conditions.

The ground or surface must be capable of supporting the scaffold and its loads

2. The ground or surface must be as level as possible.

3. Suitable matting and base plates must be used to ensure the stability of the scaffolding.

4. All pads must be of sufficient strength and thickness to support the scaffold and its loads and be in good condition.

Code Requirement.

A base or pad shall be provided at the bottom of each upright. The matting should be made of wood matting with a length of not less than 2 spans and a thickness of not less than 50mm, or channel steel can also be used.