Scaffolding Facade Protection

(1) The outer side of the scaffold is fully hung with a dense mesh safety net, the number of meshes is not less than 2000 mesh/100cm 2, the mesh body is connected vertically, and each mesh is fixed with 16# iron wire and steel pipe, and the mesh body is connected horizontally. When using the lap joint method, the lap joint length shall not be less than 200mm. The corners of the frame body should be set with wooden linings to ensure that the safety net lines at the corners of the frame body are beautiful.
(2) A 180mm foot stop is set at the bottom of the outer side of the scaffold from the second step, and a protective railing of the same material is set at the height of 600mm and 1200mm. If the inner side of the scaffold forms a limb, the outer side of the scaffold shall be protected.
(3) The surface of the outer row of scaffolding poles and large horizontal poles shall be painted with yellow paint, and the surface of the middle poles shall be painted with yellow and black two-color paint. A 200mm high warning belt shall be set up every 3 layers or 9m on the outer façade, which shall be fixed on the outside of the poles. The size of the warning tape is shown in the picture, and the surface is painted with red and white warning color paint.


Post time: Sep-29-2022


We use cookies to offer a better browsing experience, analyze site traffic, and personalize content. By using this site, you agree to our use of cookies.

Accept