Building structure safety has always been the main goal in the process of realizing various project construction, especially for public buildings. It is necessary to ensure that the building can still ensure structural safety and stability during earthquakes. The safety requirements for the erection of disc-type scaffolding are as follows:
1. The erection must be carried out in accordance with the approved plan and the requirements of the on-site briefing. It is strictly forbidden to cut corners and strictly abide by the erection process. Deformed or corrected poles shall not be used as construction materials.
2. During the erection process, there must be skilled technicians on site to guide the shift, and safety officers to follow up for inspection and supervision.
3. During the erection process, it is strictly forbidden to cross the upper and lower operations. Practical measures must be taken to ensure the safety of the transfer and use of materials, accessories, and tools, and safety guards should be set up at traffic intersections and above and below the working site according to the on-site conditions.
4. The construction load on the working layer should meet the design requirements, and it shall not be overloaded. Formwork, steel bars, and other materials shall not be concentrated on the scaffolding.
5. During the use of scaffolding, it is strictly forbidden to dismantle the structural rods of the frame without authorization. If dismantling is required, it must be reported to the technical person in charge for approval and remedial measures must be determined before implementation.
6. The scaffolding should maintain a safe distance from the overhead power transmission line. The erection of temporary power lines on the construction site and the grounding and lightning protection measures of the scaffolding should be carried out in accordance with the relevant provisions of the current industry standard “Technical Specifications for Temporary Power Safety at Construction Sites” (JGJ46).
7. Regulations for high-altitude operations:
① The erection and dismantling of scaffolding should be stopped in case of strong winds of level 6 or above, rain, snow, and foggy weather.
② Operators should use ladders to go up and down the scaffolding, and are not allowed to climb up and down the bracket, and it is not allowed to use tower cranes or cranes to hoist personnel up and down.