First, formulate a detailed dismantling plan and approve it.
The dismantling plan should include the dismantling sequence, methods, safety measures, etc., and should be approved by the technical person in charge. Before dismantling, the scaffolding should be fully inspected, and the dismantling operation can only be carried out after confirming that there are no safety hazards.
Second, carry out dismantling operations step by step in sequence
The dismantling operation should be carried out in the order of dismantling from top to bottom and layer by layer. It is strictly forbidden to operate at the same time. When dismantling, the non-load-bearing part should be dismantled first, and then the load-bearing part should be dismantled to avoid collapse accidents.
Third, prevent falling and object impact injuries
1. Wear a safety belt during dismantling operations and fix it in a reliable place to prevent falling accidents.
2. A cordon should be set up during the dismantling process, and a special person should be assigned to monitor to prevent unrelated personnel from entering the dismantling area.
3. The dismantled components should be dropped by sliding or lifting, and throwing is strictly prohibited.
Post time: Dec-11-2024