Scaffolding is an indispensable temporary facility in construction projects, mainly used to provide construction workers with a safe and stable working platform. Correct installation of scaffolding is an important part of ensuring the smooth progress of the project and the safety of personnel. The following are detailed methods and steps for scaffolding installation:
First, preparations before industrial scaffolding installation
1. Confirm the design drawings: According to the construction requirements and site conditions, refer to relevant specifications and design drawings to determine the structural form, size specifications, and erection height of the scaffolding.
2. Material inspection: Conduct a comprehensive inspection of the steel pipes, fasteners, bases, scissor braces, and other accessories to be used to confirm that there are no cracks, deformations, rust, and other problems, and ensure that their strength meets the use requirements.
3. Site cleaning: Clear obstacles in the construction area and ensure that the ground is flat and solid to facilitate the stable construction of the scaffolding.
Second, steps for industrial scaffolding installation
1. Place the base: Place the base in the preset position and level it with a level ruler to ensure the stability of the base.
2. Constructing the vertical poles: insert the vertical poles vertically into the base, keep the specified spacing between adjacent vertical poles, and fix them with right-angle fasteners.
3. Installing the crossbars: install the large and small crossbars on the vertical poles according to the design elevation, and also use fasteners to fix them to form a stable frame structure.
4. Setting up diagonal braces and scissor braces: to enhance the overall stability of the scaffolding, it is necessary to set up diagonal braces or scissor braces, which are cross-fixed between the two vertical poles.
5. Installing wall connecting parts: firmly connect the wall connecting parts between the scaffolding and the main structure of the building to prevent the scaffolding from shifting sideways.
6. Interlayer protection: after a certain number of scaffolding layers are built, interlayer protection facilities such as skirting boards, railings, and toeboards should be installed.
7. Comprehensive inspection and acceptance: after the overall installation of the scaffolding is completed, a strict quality and safety inspection is required to confirm that all connection parts are tightened and reliable and that the overall structure is stable and meets the design and safety specifications.
Through the above rigorous installation steps, it is ensured that the scaffolding plays the due supporting role in the construction process, and at the same time, it also guarantees the safe working environment of the construction workers. In actual operation, it is necessary to strictly follow the regulations, achieve scientific construction and put safety first.